Case Studies

Swords Wastewater Treatment Plant Phase 2 Expansion

Client: Siac / Aecom
Services: Temporary works design, supply and installation of ground support system

Since completion of the Phase 1 expansion works in 2003, growth in the Swords catchment has outstripped the treatment works’ current capacity, causing it to operate above its maximum design of 90,000 population equivalent. The Phase 2 expansion and upgrading the treatment plant aims to reduce the level of pollutants discharging to the receiving water (the inner Broadmeadow estuary) and to allow capacity for the growing population and projected commercial development of the greater Swords area.

Working for Siac / Aecom, Trench Control designed and installed ground support systems for large storm holding and retention tanks and a number of smaller ancillary tanks and structures. In addition, Trench Control provided other temporary works and geotechnical design services for the project. The ground support systems provided included sheet piles for 4m to 5m retained height in cantilever (unpropped) as well as sheet piles and trench sheets to with hydraulic propping elements for other structures.

Swords-Wastewater

Share:

More Posts

Balmostone, Donabate, Co Dublin

Glenveagh Homes commenced construction of 1,200 new homes at Balmoston,a 32 hectare site in Donabate, North Co Dublin. The first phase of construction consists of 432 affordable, private, cost rental and social homes. As part of the civil infrastructure for this site, Glenveagh has to install a deep water attenuation tank to manage the surface water run off more than

Bennetstown, Dunboyne, Co Meath

Rossmore Civil, working directly for Glenveagh Homes on a housing development in Dunboyne to construct 578 new homes, appointed Trench Control Ltd to design and install a 23m x 21m cofferdam with additional 5.5m x 10m pumping chamber annex to a dig depth of 6.5m. The ground conditions were particularly hard with localized boulder clay, therefor TCL needed to pre-auger