Case Studies

Ballyrickard Wastewater Treatment Plant (Project Omega)

Client: Laing O’Rourke
Services: Temporary works design, supply and installation of ground support system

Project Omega is one of the UK’s largest Public Private Partnership (PPP) schemes providing a fifth of Northern Ireland’s wastewater treatment capacity. It also handles the entirety of its sludge disposal. The scheme is intended to form a sustainable wastewater strategy to meet the Province’s needs for the next 25 years.

The project included upgrading six existing wastewater plants – at Ballynacor, Bullays Hill, Seagoe, Armagh, Richhill and Ballyrickard – refurbishing a number of sludge facilities and constructing three pumping stations and associated transfer pipelines. The project cost was £122m – strong competition throughout the tendering process and the high degree of innovation encouraged by the PPP performance criteria having yielded savings of more than 17% of the original £154m capital estimate.

Working for Laing O’Rourke, Trench Control designed and installed a large cofferdam as part of the upgrade of Ballyrickard Wastewater Treatment Plant. The cofferdam included 10m long sheets standing in cantilever (unpropped) and a scheme of ground anchors as the anti-floatation mechanism.

Ballyrickard-Wastewater

Share:

More Posts

Balmostone, Donabate, Co Dublin

Glenveagh Homes commenced construction of 1,200 new homes at Balmoston,a 32 hectare site in Donabate, North Co Dublin. The first phase of construction consists of 432 affordable, private, cost rental and social homes. As part of the civil infrastructure for this site, Glenveagh has to install a deep water attenuation tank to manage the surface water run off more than

Bennetstown, Dunboyne, Co Meath

Rossmore Civil, working directly for Glenveagh Homes on a housing development in Dunboyne to construct 578 new homes, appointed Trench Control Ltd to design and install a 23m x 21m cofferdam with additional 5.5m x 10m pumping chamber annex to a dig depth of 6.5m. The ground conditions were particularly hard with localized boulder clay, therefor TCL needed to pre-auger