Case Studies

Flintshire Bridge Converter Station, Wales

Client: John Sisk & Son
Services: Temporary works design, supply and installation of ground support system

John Sisk & Son appointed Trench Control to design and install ground support measures to facilitate the construction of three service tanks for the proposed Western Link Interconnector Project.

The works comprised three excavations for a Dump Tank and two Oil Interceptors. The Dump Tank was the larger element with excavation dimensions of 20.65m x 11.05m with an excavated depth of 5.735m. The Oil Interceptors excavations were 8.65m x 3.85m and 9.85m x 3.85m on plan dimension and 3.365m and 3.77m deep respectively. The excavations were supported using sheet piles. The Dump Tank were braced using hydraulic frames and the Oil Interceptors were not propped.

Commenting on the works, Sisk’s design manager Brian Dillon said the following: “We’ve worked with Trench Control on the Flintshire Bridge Converter Station Project and we’ve found them to be very knowledgeable both in the planning and the execution of their works.”

cs5

Share:

More Posts

Adare Bypass, Co. Limerick

The Adare Bypass is part of a Sisk Sorenson joint venture to complete 7km of motorway from Foynes to Limerick City by June 2027 at an approx. cost of €150m. One of the projects key objectives is to remove the congestion from the N21 prior to the hosting of the RyderCup at Adare Manor September 2007. Trench Control were asked

Naas, Co. Kildare

The first outing on site for our new side grip vibro hammer which installed 5-6.5m sheets into medium dense ground conditions for Glebe Builders in Naas. The old store was demolished in early April to make way for newlarger supermarket but the boundary line required to retained temporarily whilst a new RC wall could be constructed for the new structure.